The City of Moose Jaw's weekly High Street Update projects a smooth and ready High Street by early/mid-August.

The 300 and 400 blocks of High Street have been paved, painted, and fully reopened to all vehicle and foot traffic. The 700 block is currently closed in both directions due to sewer connections work and will be opened when it is completed, backfilled and temporarily paved.

The 600 block is restricted to two lanes for the same reason. Both those projects are expected to be finished by July 27th.

Final paving for the 500 to 800 blocks will be beginning July 30th.